Martin Stadium Renovation

Latest Images:




View all

Project Description:

Martin Stadium Renovation consists of four phases including components at the East End Zone, South Concourse and North Concourse.

Phases I and II have just been completed and are now in Punch List phase.

Phase I East End Zone component includes a main entry façade along Stadium Way, a new concourse with restrooms and concessions and a new ADA seating section. Phase I South Concourse includes two new restrooms, additional circulation space and new entry gates. Phase II North Concourse includes a new concourse with restrooms and concessions and a considerable increase in circulation space. This work was completed for the 2008 football season.

Phase III, the premium seating above the existing North Stands will be a separate project in the future.

Phase IV, an upper concourse with service amenities and additional stadium seating will be a seperate project in the future.



Project Team:

Current Project Phase:

  • Phase Name: Close-Out
  • Phase Start Date: 9/22/2008
  • Phase End Date: 9/18/2009

Contact Information:

Miscellaneous Dates:

  • Project Completion Date: 8/31/2008
  • Construction Start Date: 12/04/2006

Project Costs:

  • Total Project Budget: $22,500,000
  • Estimated Construction Costs: $17,000,000 -
  • Construction Costs:

The information for this project was last updated on 9/23/2008 by Louise Sweeney